Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the acf domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/cngservices.co.uk/httpdocs/wp-includes/functions.php on line 6121
Fordoun - CNG Services
Linkedin Logo
CNG Refinery CNG Refinery CNG Refinery
Fordoun Bio-CNG Mother Station

Project

Fordoun

Client

Air Liquide

Completion

September 2019

Project Outcomes

  • First ‘self-lay’ connection to National Grid NTS network by a third party.
  • National Grid Transmission completed a conceptual design study (CDS) at the NTS block valve site.
  • CSL made the case to National Grid that an ROV was not required, hence neither was an RTU on the block valve site, saving £200k.
  • The design of an off-take connection and private pipeline connecting to the 84 bar NTS network.
  • Construction was completed in September 2019. The boundary between the National Grid owned connection and private pipeline will be delineated by an insulation joint.
  • This will significantly reduce compression costs relative to typical CNG stations.