Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the disable-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/cngservices.co.uk/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the limit-login-attempts-reloaded domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/cngservices.co.uk/httpdocs/wp-includes/functions.php on line 6114
Euston - CNG Services
Linkedin Logo
Services health safety Services health safety Services health safety

Project

Euston

Client

Euston Biogas Ltd

Completion

2015

Project Outcomes

  • A 7 bar pipeline was installed to reduce capital expenditure. It was significantly cheaper and easier to build an intermediate pressure pipeline than a high-pressure pipeline
  • The remote compound was built to house compressors and an ROV, where gas is compressed to 42 bar and injected into the network. This was the first use of this particular layout in the UK
  • It was decided to manage the risk of having out-of-specification gas trapped in the pipeline in the event it was rejected at the GEU, negating the requirement for a remote reject line